Wednesday, 3 February 2010

Schedule for the project

Notes on schedule:

1st - 5th of Feb - PRE-VISUALISATION

Production design photos, storyboard and animatic.
Animatic uploaded by 4.10pm Fri 5th Feb

8th - 12th of Feb - TEST-FOOTAGE
Location shooting, lip-synch run-throughs and lighting tests.
Rushes uploaded by 4.10pm Fri 12th Feb

15th - 19th of Feb - HALF-TERM
Using stills and test-footage to create individual ideas for digipak and poster.
Ancillary Task Drafts to be uploaded by Sunday 21st Feb

22nd - 26th of Feb - FILMING (incl. weekend of 27/28th)
Feedback on rushes then complete location and studio shooting.
All filming complete by Mon 1st Mar

1st - 5th of March - POST-PRODUCTION
Digital Editing at Coleridge and Graphic Design at Long Road.
Full day editing at CR on Fri 5th Mar.
Rough Cut uploaded by 4.10pm Fri 5th Mar

8th - 12th of March - PRODUCTION DEADLINES
Rough Cut feedback then Digital Editing at Coleridge and Graphic Design at Long Road.
Full day editing at CR on Weds 10th and Fri 12th Mar.
Ancillary Tasks complete by 12.20pm Thurs 11th Mar
Music Video complete and uploaded by 4.10pm Fri 12th Mar

15th - 19th of March - EVALUATION
Video and design work feedback plus evaluation mini-tasks
Evaluation mini-tasks complete by 4.10pm Fri 19th Mar
Blogs updated by Sunday 21st March